In
addition, there is a target of 40,000 solar lanterns to be achieved
in the whole country through the recently introduced interest subsidy
scheme. As per reports received till 31st December 2002,
20,207 solar home systems, 1,250 street lighting systems and 39
kWp of SPV power plants had been installed in the general
areas in the country. In addition, 5,538 solar lanterns were distributed
during this period in these areas. The targets for the north-eastern
region were 5,000 solar home systems and 50 kWp aggregate
capacity of SPV power plants, street lights and other systems. The
achievements reported under the programme in the north- eastern
region including Sikkim as per reports received till 31st
December 2002 are 480 solar home systems and 3,125 solar lanterns.
|